Posting Costs to Work Orders

When you display the Costs tab of the Work Order Notebook, you see current information, including the last transaction posted. Costs being posted to a work order can originate from various sources.

To Post Costs to Work Orders:

1.

Perform a search from the Work Order Search window and select one of the entries displayed.

2.

Click the Go To button and select Cost Posting.

Note: Transactions shown at the top of the window display values previously posted for the selected work order.

3.

Enter transactions by selecting from the Type dropdown list in the block at the bottom of the window.

4.

Enter the appropriate data in the Amount, Document, and Remarks fields.

5.

Repeat steps 3 and 4 as many times as needed.

6.

Click OK.