Entering Remaining Hours

You can enter remaining hours by resource for one or more work orders from the Work Order Remaining Hours window. This window lists all resources planned for each work order and shows the planned hours and the actual hours used. The actual hours are updated through daily entries to the Worker Time Reporting window. You cannot make changes to work orders whose status is 70 or greater (Completed, Closed to Charges, or Cancelled).

To Update Resource Remaining Hours:

1.

From the TabWare Power Panel, select Work Orders.

2.

When the Work Order Search window appears, perform a search and highlight the work orders that need to have remaining hours updated. Click Go To and select WO Resource Remaining Hours.

3.

Select the Remaining Hours column for the resource to change and enter the revised number of remaining hours.

4.

Repeat step 3 for other resources as necessary.

5.

Click OK.